We have successfully delivered and supported multiple high-voltage transmission line projects in India like 220kV D/C Tidong HEP (150 MW) Himachal Pradesh, 400kV D/C Transmission Lineย Solapur Maharashtra, 765KV Drone Stringing Pune-Maharashtra and 765kV Angul Survey & pre-bidding design engineering, Sundargarh Transmission Line, combining drone technology with strong execution and consultancy expertise.

220kV D/C Transmission Line โ Tidong HEP (150 MW), Himachal Pradesh
Scope: 16 km line construction, tower works, conductor & OPGW stringing, testing & commissioning
๐
Commissioned: 7th March 2026

765kV Angul โ Sundargarh Transmission Line , Odisha India
Scope: Pre-bidding survey, design engineering & BOQ Report along with rates
๐
Completed: September 2025

400kV D/C Transmission Line โ Solapur, Maharashtra
Scope: Consultancy & supervision for Transmission line conductor Stringing along with drone-based stringing to avoid ROW constraints
๐
Completed: February 2026

765kV Transmission Line from Pune, Maharashtra to Karnatak Border
Scope: Multi-span drone stringing operations for transmission line conductor stringing.
๐
Commissioned: Ongoing
We have built a strong track record in Nepal among the only companies in the region to have constructed and commissioned 15+ complete transmission line projects just within 5 years delivering full transmission line construction and advanced drone operations across some of the countryโs most extreme and high-altitude terrains from TAPLEJUNG (East Nepal to SOLUKHUMBU Corridor (Central Nepal) up to MAHAKALI, DARCHULA (West Nepal).
Our experience spans working with leading hydropower developers, executing projects from survey & design to construction and commissioning.

DRONE STRINGING
CLIENT: RS INFRA PROJECTS - NEA
Scope: Drone Stringing for valley crossing of longest span of 1040m and others
Promotional video recoding of complete line
โ
Completed: February 2026

DISTRIBUTION LINE CONSTRUCTION
Scope: 1500 km conductor stringing & 5,000 pole erection, Transformers installation and Line Charging of 6 Gaunpalikas of Darchula District
Coverage: Gaunpalikas- DUHU, MAHAKALI, MALIKARJUN, LEKAM, MARMA, SHALYASIKHAR
โ
Completed & Commissioned: June 2025

TRANSMISSION LINE CONSTRUCTION
CLIENT : PRO SOLUTIONS PVT LTD & SEPCO 1 China - NEA
Scope: 8 km conductor/OPGW stringing & tower erection .
โ
Completed: December 2024

TRANSMISSION LINE CONSTRUCTION
CLIENT: Cosmic Electrical- SANIMA HYDRO
SCOPE: Complete 24 tower erection, 9km Line of conductor & OPGW stringing up to Dhunge Sanghu substation, Taplejung & commissioning
โ
Completed & Commissioned: April 2024
(Full Transmission Line Constructed by JUNIOR Teslax)
Copyright ยฉ 2026 Jr Teslax